Friday, 1 November 2019

Adobe AD0-E200 Question Answers | Get Ready For High Score

Question: 1

How many development instances does Adobe Launch allow?

A. Unlimited
B. Ten
C. Three
D. One

Answer: C

Question: 2

An analyst is copying settings from a report suite to a new report suite. Which settings are copied over to a new report suite? Select two.

A. Evar
B. VISTA rules
C. Enable transaction ID Recording
D. Pathing on variable
E. Classification

Answer: B

Question: 3

Who approves third-party extensions in Adobe Launch?

A. Enable tag link
B. Adobe customer Care
C. Internal marketing Teams
D. Adobe publisher Tool

Answer: D

Question: 4

Which tool do you recommend an analyst use to directly import, create maintain a dashboard in excel in the efficient manager?

A. Ad Hoe Analysis
B. Report Builder
C. Analysis Workspace
D. Data Warehouse

Answer: B


0 comments:

Post a Comment

Note: only a member of this blog may post a comment.